Lift Planning — Load Weight, Centre of Gravity, Sling Angles
Every lifting operation — no matter how routine — requires planning. A lift plan documents the key parameters of the lift and ensures that all factors have been considered before the load leaves the ground.
Determining Load Weight
Accurate load weight is the single most important factor in lift planning:
- Check manufacturer’s documentation for equipment weight
- Calculate weight from material density and dimensions for structural elements
- Account for additional weight — formwork, attached fittings, moisture content
- Never estimate — always verify the weight before lifting
- Include the weight of slings and rigging hardware in your calculations
Centre of Gravity (COG)
The centre of gravity determines how the load will behave when lifted:
- The hook must be positioned directly above the COG for a balanced lift
- Irregular or asymmetric loads require careful COG calculation
- If the COG is offset, the load will tilt when lifted — this can cause it to slip out of slings
- For complex shapes, consider using a spreader beam or lifting frame to distribute the load evenly
Sling Angles and Their Effect on Load
This is a critical concept that many workers underestimate. The angle of the sling to the vertical dramatically affects the force on each sling leg:
| Sling Angle to Vertical | Load Factor | Force on Each Leg (for 1-tonne load, 2-leg sling) |
|---|---|---|
| 0° (vertical) | 1.00 | 500 kg |
| 30° | 1.15 | 577 kg |
| 45° | 1.41 | 707 kg |
| 60° | 2.00 | 1,000 kg |
Rule of thumb: Never use sling angles greater than 60° from vertical. At 60°, each sling leg bears the full weight of the load. Beyond 60°, the forces become dangerously high.
Key Elements of a Lift Plan
- Load description, weight, and dimensions
- Crane type and capacity at the required radius
- Sling type, capacity, and configuration
- Pick-up and set-down locations
- Ground conditions and outrigger positions
- Proximity hazards (power lines, structures, other cranes)
- Weather conditions and wind limits
- Personnel roles and communication method